Arbitration Practice in Construction ContractsRoutledge, 2. sept 2003 - 232 pages Considers each stage in the course of an arbitration in detail, from the claimant's decision to seek the means of resolving a dispute to the arbitrator's award, explaining clearly and concisely what is expected of the claimant, respondent and arbitrator and when. |
From inside the book
Results 1-5 of 38
Page
... where necessary . All in all , this is a book which is designed to provide the reader with as much practical information as possible about arbitration law and procedure , in an accessible form , and within a modest compass Foreword.
... where necessary . All in all , this is a book which is designed to provide the reader with as much practical information as possible about arbitration law and procedure , in an accessible form , and within a modest compass Foreword.
Page 15
... possible , because of their likely disruptive effect on progress . The third change imposes upon the parties the obligation to comply with the ICE Arbitration Procedure ( 1983 ) , which Procedure is discussed below . Conciliation The ...
... possible , because of their likely disruptive effect on progress . The third change imposes upon the parties the obligation to comply with the ICE Arbitration Procedure ( 1983 ) , which Procedure is discussed below . Conciliation The ...
Page 18
... Form deals with this situation as far as it is possible to do so , by requiring the subcontractor to accept the arbitrator The FIDIC conditions of contract 19 appointed under the main 18 Arbitration agreements The FCEC Form of Subcontract.
... Form deals with this situation as far as it is possible to do so , by requiring the subcontractor to accept the arbitrator The FIDIC conditions of contract 19 appointed under the main 18 Arbitration agreements The FCEC Form of Subcontract.
Page 19
... possible for the main contractor to use this subclause to ensure that the two references are referred to the same arbitrator . Where the dispute originates as a claim by the subcontractor consolida- tion of a corresponding dispute ...
... possible for the main contractor to use this subclause to ensure that the two references are referred to the same arbitrator . Where the dispute originates as a claim by the subcontractor consolida- tion of a corresponding dispute ...
Page 22
... possible , in order to defer the day of settlement . The strategy usually adopted in such cases is to ignore the arbitrator's orders or to apply for excessive periods of time for preparation of pleadings ; to apply for extensions ; to ...
... possible , in order to defer the day of settlement . The strategy usually adopted in such cases is to ignore the arbitrator's orders or to apply for excessive periods of time for preparation of pleadings ; to apply for extensions ; to ...
Contents
The award | 56 |
Types of award | 59 |
Format of the award | 61 |
Interest | 65 |
Publication of the award | 66 |
Costs | 67 |
Responsibility for cost | 68 |
Offers to settle | 69 |
17 | |
18 | |
19 | |
20 | |
21 | |
22 | |
24 | |
Power to revise engineers decisions | 25 |
Appointment of the arbitrator | 26 |
Qualifications of the arbitrator | 27 |
Terms of the appointment | 28 |
Supplying vacancies | 29 |
Preliminaries | 31 |
The preliminary meeting | 32 |
Pleadings | 33 |
Amendments of pleadings | 35 |
The Scott Schedule | 36 |
Privilege | 37 |
Transcript of the hearing | 39 |
Conduct of interlocutory stages | 40 |
Liberty to apply | 41 |
Small claims | 42 |
Evidence | 43 |
Admissibility of evidence | 46 |
Proofs of evidence | 47 |
Burden and standard of proff | 48 |
The hearing | 49 |
Courtesy | 50 |
Procedure | 51 |
Failure to award cost | 71 |
Avoiding unnecessary taxation | 73 |
Cost of the award | 74 |
Finality of the award enforcement appeals | 75 |
Amendments to deal with costs | 76 |
Reasoned awards | 78 |
The contractor as claimant | 81 |
The acceptance | 83 |
Letters of intent | 84 |
The construction period | 85 |
Claims | 86 |
Disputes | 87 |
Selection of the arbitrator | 89 |
The preliminaries | 90 |
The hearing | 92 |
Request for reasoned award | 93 |
Upsetting the award | 94 |
Specimen documents | 95 |
The Arbitration Act 1950 | 142 |
Arbitration Act 1975 | 173 |
Arbitration Act 1979 | 178 |
The Rules of the Supreme Court Amendment No 3 1979 | 188 |
The Arbitration Act 1979 Commencement Order 1979 | 194 |
Interest tables | 196 |
Flow chart | 203 |
Bibliography | 205 |
Table of Cases | 207 |
Index | 209 |
Other editions - View all
Common terms and phrases
acceptance accordance action additional agreed allegation amended amount appeal application appointment Arbitration Act arbitration agreement arbitrator or umpire arbitrator's arising authority award Chapter Civil Engineers claim Claimant Clause commencement completion construction continued contract contractor Convention copy costs counsel Counterclaim course deal decision Defence delay determine directions dispute documents effect enforcement ensure entitled event evidence example expert extension fact fails fees final further give given hearing High Court ICE Conditions incurred Institution intention interest interim issues judge knowledge leave letter Limited matters means meeting month namely necessary notice offer otherwise paragraph parties payment period person pleadings Points possible preliminary prepared present President procedure proceedings provision question question of law reasons reference relation relevant represented request respect respondent rules Schedule served submission submitted tender unless usually valid witness writing